Electrical Engineer and Construction Supervisor

Available
Serial No: 4662
Skills keywords: engineering, pre commissioning, QAQC, supervising
Current location:  United States - View on map

Company:  COSTA NORTE COMPANY - Urea Plant-PEQUIVEN

PMF Project-Toyo Engineering Corporation - Carabobo,Venezuela

Date:     April 2012  to  December 2012

Position:  Electrical Engineer, Field Construction Supervisor

Company: Inelectra - Maracaibo, Venezuela

Date:     May 2011  to  February 2012

Position:  Electrical Engineer

Project:  Cogeneration Plant and Osmosis Treatment Plant

Responsibilities: Detail engineering for the electrical system of the Plant

Company:  BERTH 6 QG 3&4 (Qatar Gas) Raslafan City - Qatar, Doha

Date:  March 2009  to  March 2011

Position:  Electrical, Instrument and Telecomm Field Engineer Supervisor Leader

Project:  Common Lean LNG Loading Facilities (Berth 6)

Responsibilities: Supervise  the E,I &Tconstruction, QAQC and pre commissioning activities.

Company:  BOHAI Phase II Development - (ConocoPhillips) - Flour Daniels (Sugar Land, TX)

Sembawang Shipyard,Singapore

Date: July 2005  to July 2008

Position:  Electrical Supervisor

Project:  Bohai Phase II Development  (FPSO, Top Side)

Responsibilities: Supervise  the Electrical construction activities and control the cable tray installation and cable pulling for the different systems (medium and low voltage, control, communication and telecomm), final HUC and turnover to the commissioning group.  Material controller.

Company:  Alliance-Engineering/NM WoodGroup.

Date: November 2004 to April 2005

Position:  Electrical Engineer

Project: Oil Bird Field Development, EOG Resources Ltd.

Responsibilities: Electrical Design of lighting system for process areas, Electrical Load study,  cable routing and cable tray for low Voltage, control circuit design for AC motor, Electrical hook - up, Job metric calculation, Equipment  specs.

Company:  CLJOC(Cuulong Joint Operating Company) - (ConocoPhillips)

c/o Samsung Heavy Industries - Gyeongnam, Korea - Ho Chi Minh City, Vietnam

Date:  September 2002 to present December 2003

Position:  Electrical Supervisor

Project:  Su Tu Den Project (FPSO)

Responsibilities: Supervise  the Electrical construction activities and acted as the QA/QC supervisor on the installation of facilities, final HUC and turnover to the Operations group. Facilities included 4160 Vac Power Generation and Distribution System, 450 Vac Power and control installation for Top Side and Marine System, Lighting System, LP flare system, Gas compression units,  produced water facilities and electrostatic treater.

Company:  PETROZUATA. (Conoco/PDVSA) - Puerto La Cruz - Edo. Anzoategui-Venezuela

Date:  January 00 to August 02

Position:  Instrument/Electrical Superintendent

Project:  Phase 3 PETROZUATA

Responsibilities: Supervise  the I/E construction activities and acted as the QA/QC supervisor on the installation of the secondary oil production facilities from the design to the final HUC and turnover to the Operations group. Facilities included a LP flare system, vapor recovery unit, gas compression modules, heavy oil separation equipment, produced water facilities and electrostatic treaters.

Company:  THRONSON INTERNACIONAL DE ENEZUELA.Maracaibo - Edo. Zulia

Date:  December 97- January 00

Position:  Instrument/Electrical Supervisor

Project: Venezuela Extra Heavy Oil. CONOCO-MARAVEN (PETROZUATA)

Responsibilities: Supervised construction crews and acted as the company QA/QC supervisor on the electrical system installation of a 54MW gas turbine facility, 34.5kv distribution system and all electrical systems in the medium and low voltage classes for the well pad and primary production facilities. Primary role was to handle the Interface between the field construction crews, Field Superintendent and the Engineering contractor.

Company:  THRONSON INTERNACIONAL DE ENEZUELA.Maracaibo - Edo. Zulia

Date:  August 96 – December 97

Position:  Electrical Engineer

Project: Venezuela Extra Heavy Oil. CONOCO-MARAVEN (PETROZUATA)

Responsibilities: Electrical system design for the 120,000 bbl Main Station facilities lighting systems, grounding net calculation, cable tray design/routing for the facility power/control/instrument systems. Engineering activities also included the control circuit design for AC motor circuits, Electrical Classification of Hazardous Locations, instrument location & electrical hook - up, job metric calculations, and construction installation specs.

Company:  TECSER INGENIERIA, C.A.Maracaibo - Edo. Zulia, Venezuela

Date: June 95 - July 96

Position: Electrical Engineer

Project: Cold Water System. PEQUIVEN. El Tablazo. Venezuela.

Project: Gas Compressor Installation. FIOR DE VENEZUELA. Pto. Ordaz

Project: Planta de Deshidratación de Crudo y tratamiento de Aguas de Afluentes. “La Colina”. Tecpetrol de Venezuela,S.A.

Project: Off Shore Pump Station PB-12.5, Tecpetrol de Venezuela, S.A.

Project: Oil Pumping System. La Colina. El Calvario y El Capitan, Tecpetrol de Venezuela, S.A.

Responsibilities: Electrical Design of lighting system for process areas, grounding net calculation, cable routing for low Voltage, control circuit design for AC motor, Electrical hook - up, Job metric calculation, construction specs.

Company:  MATEL (Electrical Materials) Maracaibo – Venezuela,Venezuela

Date: January 94 -May 95

Position: Salesman and Support Technical on Electrical Equipment.

Company: INSTRUVAL - Valencia - Venezuela

Date: July 93 - January 94

Position: Salesman and support technical on actuators, levels switch and transducers.

Company: COSA - INGENIEROS CONSULTORES, Maracaibo - Venezuela

Date:November 90 - June 93

Position: Electrical Engineer

  1. Project: GLP Fractionating Plant Retrofit: Bajo Grande, MARAVEN, S.A. Venezuela.
    Responsibilities: Electrical Design for Lighting System in Control Room, 24 kV Ducts, Cable Routing for Low voltage, UPS Specs. Feeder Panel Boards Specs.
  2. Project: Vapor Recovery System for Crude Flow Station Cl - 1, LAGOVEN, S.A., Maracaibo, Lake, Venezuela.
    Responsibilities: Electrical Classification of Hazardous Locations, Lighting System for Process Areas, Grounding Net Calculation, Cable Routing for L.V. & M.V., Control Circuit Design for AC Motors, Electrical Hook -up, Job Metric Calculations, Construction Specs
  3. Project: Pilot Plant for Orimulsion Process, Zuata - MARAVEN, S.A. Venezuela.
    Responsibilities: Cable Routes, Grounding Nets, Electrical Hook - up, Equipment specs.
  4. Project: Zuata Development, Orimulsion Process, MARAVEN, S.A. Venezuela.
    Responsibilities: Electrical Classification of Hazardous Locations, Grounding Nets, Electrical Hook - up, Lightning System, Material Take - off & Equipment

Spoken languages: Spanish english