CV, Lead QA, QC Engineeer For Energy And Petrochemical Industries

Unavailable
Serial No: 18165
Skills keywords: project engineer, welding inspectors

Short Bio:

I am a lead QA/QC mechanical engineer specify in industrial project ( oil & gas , power station , petrochemical and workshops plat,steel structure and piping fabrication) and fast track project.I have 11 years experiences in the field with multi international companies in and out Egypt . i have my QA/QC qualification (CSWIP 3.1,VT,RT,UT,PT AND MT), SAFETY qualification (OSHA and other British safety courses and certifications)plus others in management as shown in the C.V

Current location:  kuwait - View on map
Nationality: egyptian
Preferred Sector of Employment:  Oil, Gas and Energy
Spoken languages: Arabic, english, italian
Location I am interested in working: Anywhere

Qualifications

■ B.Sc. Mechanical Engineering.
Graduation project “water treatment stations”: excellent.

Career  Summary

COMPANY : Alghanim International co (EPC company)
(JULY 2014 till NOW)
PROJECT: SABIYA OCGT power plant
CLIENT: MEW (Ministry of Electricity and Water ) KUWAIT.

JOP TITLE: – Lead QA/QC Engineer.

TASKS: – LEAD THE MECHANICAL QUALITY TEAM TO ATCHIEVE THE PROJECT QUALITY PLAN IN PIPING AND PAINTING ACTIVITIES.

COMPANY : Drake & Scull Construction.
(DEC 2012 till JUNE 2014)
PROJECT: EHC LDAN Project (Ain Sukhna)(petrochemical)
CLIENT: EHC (EGYPTIAN HYDROCARBON COMPANY)
MAIN CONTRACTOR : ThyssenKrupp UHDE GmbH.

JOP TITLE: – SENIOR QA/QC Engineer.

TASKS: – RESPONSIBLE FOR THE QUALITY CONTROL ACTIVITY OF THE PIPING / EQUIPMENT MECHANICAL CONSTRUCTION WORK.

COMPANY : KHARAFI NATIONAL (KN) (EPC)
(DEC 2010 till MAY2012)
(For Mechanical& Electrical Works S.A.E)
PROJECT: ELSHABAB SIMPLE CYCLE GAS TURBINE UNITS (G.E) (Fast track project) (Power Project).
CLIENT: EAST DELTA COMPANY (EDEPC).
CONSULTANT: PEGASCO.

ABOUT THE PROJCT: The project is one of power plant projects to build a new 1000-MW (G.E ) eight units simple cycle gas power plant at ELSHABA (ISMAEALIA).

JOB TITLE: -QA/QC ENGINEER.

TASKS: – RESPONSIBLE FOR THE QUALITY CONTROL ACTIVITY OF THE MECHANICAL CONSTRUCTION WORKS IN ALL 9E TURBINES UNITE (AUX., TURBINE, GENERATOR, PIPING, STACK (PLATE WORKS), STEEL STRUCTURE AND OTHER SKIDS).

COMPANY : PROCTER & Gamble (P&G).
(JUN 2010 till DEC 2010)
PROJECT: THE NEW PRODUCTS EXTENTION (BAR SOAP BIULDING) (industrial) (projects).
ABOUT THE PROJCT: The project one of new extensions for the Cairo plant to serve the production targets, the project contains c.s & s.s piping(f.f and compressed air system), equipment (compressors, blowers and pumps) ,ducts &plat work in the dust control systems and steel structure work.

JOB TITLE: – SITE MECHANICAL MANAGER (Resident Engineer for the Client).

TASKS: – RESPONSIBLE FOR MANAGE, ARRANGE, MONITORING AND RECEIVING THE MECHANICAL CONSTRUCTION WORKS (EQUIPMENTS, PIPING AND STEEL STRUCTURE) AND FOLLOW UP THE CONTRACTORS PERFORMANCE. (Safety, Quality and progress).

COMPANY : (VSA) Consortium (QATAR). (EPC)
(DEC 2008 till JUN 2010)
Veolia water (P) Saipem(E) Aljaber(C)
CLIENT: SHELL & QATAR GAS
PROJECTS: PEARL GTL (Gas to Liquid) (Oil &Gas field).

ABOUT THE PROJCT: The project is the world’s largest gas to liquids (GTL) plant; Pearl GTL is a major step towards meeting the world’s growing demand for cleaner energy. The plant, a joint development by Qatar Petroleum and Shell.

JOB TITLE: -SENIOR QA/QC ENGINEER (workshop &site).

TASKS: -RESPONSIBLE QA/QC PIPING AND PAINTING TASKS.

Piping

Responsible for the piping works:-

– Metallic C.S, S.S.

-Non metallic GRP.

(Fabrication and erection) According to SHELL specifications and standards.

Attend in piping two star audits.

Applied the weekly Surveillance for piping FSI (flawless startup initiative) with shell representative and taking the corrective action.

Painting

Monitoring the painting subcontractor (KAEFER) to apply SHELL painting systems in the gulf area ambient conditions with all respect to SHELL requirements in FSI and preservation. With HEMPEL as paints vendor.

Prepared / Attend in piping and painting star audits.

COMPANY : ALEX FIBER (AFCO).
(AUG 2008 till DEC 2008)
PROJECTS: – LINES II &III.( petrochemical)
ABOUT THE PROJCT: The project is the only Acrylic Fiber plant in Africa and Middle-east region, The plant has the most modern acrylic fiber manufacturing technology from Japan Exlan. The basic engineering done by Kawasaki Heavy Industries Limited, Japan. The basic work conditions same as the petrochemical plant.

JOB TITLE: – QUALITY CONTROL MANAGER(for the client).

TASKS: -RESPONSIBLE FOR ALL QA/QC TASKS (PIPING, INSTRUMENTES, TANKS, PUMPS AND EQUIPMENTS) AND FOLLOW UP THE CONTRACTORS PERFORMANCE.

Piping

Responsible for all piping works (fabrication and erection)

MECHANICAL (Equipments, Pumps, Tanks)

COMPANY : ARESCO (ASEC).
(AUG 2006 till AUG 2008)
POWER PROJECTS
PIPING
PROJECTs: – EAST DELTA ELECTRICAL PRODUCTION CAMPANY (NEW TALKHA) (CMI) (workshop)
ABOUT THE PROJCT: The project is one of power plant projects to build a new 750-MW combined cycle power plant at Talkha.

JOB TITLE: Quality Engineer& Quality coordinator.

Responsible for the final release and all documentation package for power station plant projects (Dimension, traceability, visual, internal cleaning, painting, NDT, ASME list for U or P stamp by dealing with A.I)

1 Visual inspection for welding connections.

2 Inspection for NDT methods.

CEMENT PROJECTS (EPC).

MECHANICAL ,PLATE WORK AND STEEL STRUCTURE (workshop). (AWS D1.1)& (FLS spec.)

PROJECTS: – SINA GRAY PHASE 2, (workshop& site)

– MAINTINANCE OF AMRIA FOR CEMENT (workshop),

– EL TAKAMOL – CEMENT – SUDAN (workshop),

– MASGORDN – CEMENT – SUDAN (workshop).

JOB TITLE: Deputy Q.A/Q.C Head (Q.C site manager).

TASKS: – RESPONSIBLE FOR THE QUALITY CONTROL ACTIVITY OF THE MECHANICAL CONSTRUCTION WORKS IN ALL CEMENT PLANT, HANDLING OVER TO THE CLIENT AND THE COMPANY REPRESENTITIVE IN THE OFFICIALY MEETING.

COMPANY : (I.B.S.F) INTERNATIONAL COMPANY OF MANUFACTORING BOILERS AND STEEL STRUCTURE.
(DEC 2005 till AUG 2006)
PROJECTS : – NORTH CAIRO POWER STATION (NEM) (Power Project),
– METKA (ALSTOME) (Power Project).

JOB TITLE: Quality Engineer

Fabrication the drums and the main piping of boilers.

Fabrication the main steel structure for boiler (built up sections)

The main coordinator Between (I.B.S.F) and (ESACO):

COMPANY : ARESCO (ASEC).
(NOV 2004 till DEC 2005)
Piping
PROJECTS: – ALEX FIBER (sit) LINE I. (ASME B 31.3)






popup-img